News & Analysis

550 million Euro contract in place for 28-nm node Globalfoundries Fab 2

Julien Happich

10/14/2009 3:32 AM EDT

CAMBRIDGE, UK — The international engineering company M+W Zander has been awarded a contract for approximately 550 million Euro from semiconductor manufacturing company Globalfoundries, to engineer and construct its new semiconductor wafer facility Fab 2.

The construction site is located at the Luther Forest Technology Campus in Saratoga County, New York. Fab 2 is expected to be the most advanced semiconductor manufacturing foundry in the world.

The facility will initially produce 300-millimeter-wafers at the 28-nanometer node for a variety of clients. The order for M+W Zander provides a full ‘turnkey’ solution for the construction of the facility.

As such, M+W Zander is providing full architectural and engineering services, construction management for the entire project as well as general contracting for all of the technical areas to include the manufacturing spaces, building utilities, central utility building and process systems.

The Fab 2 complex will consist of four major buildings totalling more than 130,000 square meters including a 28,000 square meters Class 100 clean room wafer fabrication building, a support building, an administrative office building and a central utility building (CUB) along with service yards and small support buildings.

Construction is expected to take about two years to complete, and 12 to 18 months to ramp to full operating mode. Initial production is expected to begin in 2012.





Please sign in to post comment

Navigate to related information

EE Buzz DesignCon

Datasheets.com Parts Search

185 million searchable parts
(please enter a part number or hit search to begin)

Feedback Form